Meritus Technology / China project support

Inspection & NDT Coordination

Meritus Technology connects dimensional verification with related quality inspection and supervision. The existing Quality service includes NDT witnessing; the project scope must distinguish witnessing or coordination from performing a test.

Illustration of ultrasonic weld examination in an industrial setting
Ultrasonic weld examination illustration for inspection coordination and witnessing. It does not establish a Meritus testing-performance capability.

Different questions. Coordinated evidence.

A dimensional survey checks geometry. NDT examines relevant material or weld indications using a method selected for the material, weld configuration, applicable code and inspection/test plan. Neither substitutes for the other.

Meritus’s existing Quality scope describes witnessing ultrasonic testing (UT), radiographic testing (RT), magnetic particle testing (MT) and penetrant testing (PT). A witnessing assignment checks agreed activities and records; it is not a claim that Meritus performs every method or holds the testing organisation’s approvals.

Before mobilisation, identify the testing party, method and procedure approvals, personnel qualification requirements, hold points and reporting responsibilities. Actual testing by Meritus must not be assumed from a coordination or witness scope.

  • Inspection/test-plan and hold-point coordination
  • Witnessing agreed examinations and reviewing the resulting records
  • Dimensional checks alongside weld and fabrication inspection
  • Clear responsibilities for testing, interpretation and acceptance
Coordinate records, annotated views and engineering reviewExplanatory schematic only. No project measurement, tolerance or performance result is represented.ILLUSTRATIVE GEOMETRY / NOT MEASURED DATAReference and acceptance criteria agreed per project
Illustrative separation of survey evidence, NDT records and engineering acceptance responsibilities.

An agreed, traceable workflow

How the work is planned and delivered

  1. Review material, weld details, applicable code and the client’s inspection/test plan.
  2. Confirm who performs the test, who witnesses it and who accepts the results.
  3. Coordinate access and hold points with dimensional survey activities where relevant.
  4. Witness agreed checks and record observations or outstanding documentation.
  5. Report to the client for disposition, follow-up or release under the project plan.
Survey inputs, datum, capture, comparison and report workflowExplanatory schematic only. No project measurement, tolerance or performance result is represented.12345ILLUSTRATIVE GEOMETRY / NOT MEASURED DATAReference and acceptance criteria agreed per project
Illustrative work-package sequence. Method, hold points and reporting are agreed before capture.

Acceptance criteria come from the client’s approved drawings, specifications and agreed survey plan. There is no universal tolerance or automatic acceptance based on the instrument used.

In-house capability, project-specific methods

Meritus Technology has an in-house technical team, equipment and software capability for projects across fabrication yards and suppliers in China. We agree the survey method, access requirements and reporting scope around each project’s integration decisions.

Instrument category and software function do not establish an automatic accuracy level. The survey plan, conditions, reference and checks determine fitness for the intended use.

Explore methods, equipment and software
Industrial laser-scanning illustration showing survey capture around fabricated structures
Illustrative laser-scanning and geometry capture concept, not a Meritus project dataset.

Practical handover

Typical outputs

Select the deliverables your engineering and QA teams can use. Formats, coordinate conventions, revision references and limitations are part of the agreed scope.

  • Witness and inspection observations within the agreed assignment
  • Hold-point status and references to the testing party’s records
  • Dimensional reports issued separately from NDT results
  • Outstanding items for client or engineering disposition
Coordinate records, annotated views and engineering reviewExplanatory schematic only. No project measurement, tolerance or performance result is represented.ILLUSTRATIVE GEOMETRY / NOT MEASURED DATAReference and acceptance criteria agreed per project
Illustrative coordinate record, annotated comparison and review pack. These are not sample project findings.

Application use cases / not project case studies

Engineering situations and the decisions they support

The following typical situations explain a survey approach. They are not claims that Meritus completed a named project. Each assignment uses the client’s approved drawings, specifications and project-specific acceptance criteria.

FPU/FPSO topside module fabrication and fit-up

Asset and fabrication stage
Separately fabricated topside modules before trial fit, lift or integration at the yard.
Dimensional problem
Structural connections and piping interfaces can be individually complete but fail to align when the modules are brought together.
Survey reference and capture method
Establish a survey control network and shared datum; capture critical interfaces, mating surfaces and support positions with total stations and/or scanning.
Analysis against design and tolerance
Transform as-built geometry to design coordinates; compare connection positions and clearances against current approved drawings and project tolerances.
Deliverables
Interface coordinate tables, annotated deviations, clash/fit-up views and a corrective-action list for engineering disposition.
Engineering decision supported
Whether to adjust a connection or module before integration, or request further engineering review.
Industrial module interface and fit-up illustration
Illustrative module interfaces and fit-up coordination, not a documented project or measured result.
Discuss module interfaces before integration

Offshore wind suction caissons and jackets during yard fabrication

Asset and fabrication stage
Cylindrical foundation and lattice structures at agreed fabrication hold points, before release or installation planning.
Dimensional problem
Roundness, verticality, straightness, flatness or interface geometry can change during fabrication.
Survey reference and capture method
Establish a measured control network; capture selected sections and interfaces with scanning and/or total stations relative to stable benchmarks.
Analysis against design and tolerance
Compare as-built profiles, axes and mating surfaces with design geometry and the tolerances specified for the current stage and measurement condition.
Deliverables
Circularity/ovality and verticality reports, deviation maps, interface records and as-built geometry for installation planning.
Engineering decision supported
Release, correction or further engineering review against the governing project tolerance.
Schematic of caisson circular sections, jacket legs and flange interfaceExplanatory schematic only. No project measurement, tolerance or performance result is represented.ILLUSTRATIVE GEOMETRY / NOT MEASURED DATAReference and acceptance criteria agreed per project
Illustrative cylindrical foundation profiles and jacket geometry; candidate yard photographs are not yet approved.
Discuss foundation geometry and hold points

Refinery vessel and process equipment fabrication/installation

Asset and fabrication stage
Vessels, columns and support interfaces through fabrication, lifting and installation.
Dimensional problem
Vessel shape and support/nozzle positions may shift, affecting alignment and the installation envelope.
Survey reference and capture method
Establish an agreed datum and capture accessible 3D as-built geometry, support points and relevant interfaces under the recorded measurement condition.
Analysis against design and tolerance
Analyse deformation and alignment relative to nominal design or a controlled baseline, using the current installation requirements and project tolerances.
Deliverables
Deformation plots, position/alignment records, annotated 3D views and recommendations for engineering review.
Engineering decision supported
Whether fabrication correction or a change in installation planning needs engineering consideration.
Refinery process-vessel survey illustration
Illustrative process-vessel geometry survey. No measured deformation or project outcome is represented.
Discuss process equipment alignment

Before you scope a survey

Buyer questions

Illustration of ultrasonic weld examination in an industrial setting
Ultrasonic weld examination illustration for inspection coordination and witnessing. It does not establish a Meritus testing-performance capability.
Can inspection and NDT be coordinated at fabrication yards in China?

Yes, coordination and witnessing can be agreed alongside the existing Quality service. Confirm the yard, inspection plan, test provider and responsibilities before mobilisation.

Does Meritus perform UT, RT, MT and PT?

The existing public Quality scope lists NDT witnessing for these methods. Performance of testing, interpretation authority and method-specific qualifications require separate confirmation; witnessing is not a claim to perform the test.

How is the NDT method selected?

The material, weld type, accessible surfaces, applicable code and approved inspection plan determine the suitable method and procedure. The responsible technical parties must approve that selection.

Is dimensional inspection a type of NDT weld acceptance?

No. Dimensional control addresses geometry, alignment and fit-up. NDT addresses the examination defined by its method and procedure. Acceptance is assessed against the relevant requirements for each.

Start with the engineering question

Discuss inspection and witness requirements

Tell us what must connect, what is already fabricated and when your team needs measured evidence. Use our existing contact flow to discuss the survey scope; there is no new survey submission form.

Include in your survey brief

  • Asset type and interfaces that matter
  • Site/yard location and access restrictions
  • Available drawings/models and revisions
  • Critical dimensions and governing tolerances
  • Fabrication or installation stage
  • Schedule, hold points and required outputs

Share confidential files through an agreed project channel, not a public page.