A hull crawler is only one part of a robotic hull preparation system. The result in dry dock depends on the pump, hoses, recovery equipment, inspection and dock schedule as much as on the robot. Shipyards and repair contractors get reliable output when they plan the whole system before the vessel arrives.

Hull geometry and obstacles

  • Curvature: the M-06 UHP Hydroblasting Crawler lists a minimum curvature of 0.5 m, climbing over 25 mm weld seams and coverage of up to 98% of the outer hull. Bow and stern areas with tighter curvature need checking.
  • Flat bottom: the M-03 PRO is designed for flat-bottom work. Keel and side blocks cover part of the bottom until they are moved.
  • Obstacles: sea chests and gratings, anodes, bilge keels, thruster tunnels, draft and load-line marks, echo sounder and log openings. Plan the manual work around them.
  • Decks: the MH-03 deck cart covers horizontal deck areas.

UHP or abrasive preparation

UHP water jetting removes coatings, rust and soluble salts without abrasive. It reveals the existing profile but does not create a new one, and it is graded under ISO 8501-4 (for example Wa 2.5) with a flash-rust grade. It suits recoating over a previously blasted hull where the coating system allows.

Abrasive blasting creates profile and is graded under ISO 8501-1 (for example Sa 2.5). The M-04 R blasts with abrasive recovery and is listed for weld-seam treatment after hull erection. Grinding and sanding with the M-05 suit seams and local areas.

The coating specification decides: required cleanliness, profile range, flash-rust limit, salt limit and whether water jetting is acceptable for the system being applied.

Pump capacity

The robot’s nozzle configuration determines the pressure and flow required. The MP-28E electric and MP-28D diesel pumps are listed at up to 2800 bar and 38 L/min, with linked remote control for start/stop, pressure release and pressure/flow adjustment. Confirm the pump suits the robot and nozzle set, the power or fuel supply on the dock, and the water quality and filtration the pump requires.

Hose routing and tethering

  • UHP hose length adds pressure loss and weight; route and support it so it does not drag the crawler.
  • Protect hoses from dock traffic, keel blocks and cranes, and inspect fittings before each shift.
  • Use a secondary safety line on the crawler and set exclusion zones below and around the work area.

Wastewater and abrasive recovery

Hull preparation releases old coating, rust and, on underwater areas, antifouling residues. The dock’s environmental permit sets what may be discharged. The MSR-04 Vacuum Wastewater Reclaimer collects rust, paint residue and wastewater from a UHP robot, one unit per robot; its page lists 2.5 t/h capacity, 15 m lift and a 0.9 m³ built-in tank with a 4–6 h cleaning interval. For abrasive work, plan containment and collection of spent abrasive.

Dock schedule

Dry-dock time is fixed and expensive. Sequence hull areas with block moves, other trades and weather. Allow time for mobilisation, setup and inspection holds, and keep a manual method ready for areas the robot cannot reach in time.

Inspection

  • Cleanliness and flash-rust grade against ISO 8501-4 or ISO 8501-1 reference photographs.
  • Profile (ISO 8503) where specified, dust (ISO 8502-3) and soluble salts (ISO 8502-6 and 8502-9).
  • Climate readings before coating, and DFT after each coat.
  • Hold points agreed with the owner’s representative and coating inspector, so robot areas are accepted promptly.

Trial productivity

The M-06 page lists 30–50 m²/h. Actual output depends on the coating being removed, the standard required, hull shape and hose management. Run a trial on a representative area and measure accepted area per shift. When comparing cost, include mobilisation, setup, support crew, water, power, recovery and disposal, as well as rework. Potential payback depends on the repeat workload.

Hull work is not cargo-hold cleaning

The MCH-02 Cargo Hold Cleaning Robot is a 500 bar water cleaning robot for bulk-carrier holds, including corrugated bulkheads. It removes cargo residues between voyages. It is not specified for coating removal to a Wa grade, and hold cleaning is planned as part of ship operation rather than dry-dock surface preparation.

embodyne.ai equipment is supplied and coordinated by Meritus Technology; Meritus does not manufacture it. Product figures quoted here are the ranges listed on the product pages, not guaranteed site results. Configuration, accessories and suitability are confirmed for each project.

Related LinkedIn discussion: M-06 hull preparation application overview. See also Magnetic Crawlers for Industrial Surface Preparation.

Meritus Technology Shanghai
Email: sales@meritustech.com
Phone / WhatsApp: +86 134 8206 1802
www.meritustech.com


Discuss with our team: sales@meritustech.com · +86 13482061802

Discussion on LinkedIn: View the original post and join the comments